Carriers slow down over Thanksgiving and Christmas. How should we plan freight around the holidays?
Carriers slow down over Thanksgiving and Christmas. How should we plan freight around the holidays?
It is the Monday before Thanksgiving. A distributor has 40 outbound orders scheduled for the week. Twelve are LTL to customers in the Southeast. The plant runs Monday to Wednesday, closes Thursday and Friday, and reopens the next Monday. On Wednesday afternoon a coordinator learns that one LTL carrier's destination terminal is closed Thursday and Friday, and two customers' receiving docks will not open again until Monday. Six pallets picked up Wednesday will sit in a terminal for four days. One customer needed them for a Friday production run.
Plan holiday freight by building one calendar of every closure that touches a load, pulling pickups forward so freight lands before receivers close, confirming each load's dates in writing and naming who decides while the team is out. The holidays are not one closure. They are several closures at different places, and a load only moves when the plant, the carrier and the receiver are all open at the right time.
The problem is rarely that nobody knew Thanksgiving was coming. The problem is that each party's schedule lives in a different place. The plant knows its own shutdown. The carrier sends a holiday notice to a shared inbox. The customer's receiving hours sit in an email from last year. Nobody puts them side by side until a load fails.
Why the holidays are harder than a normal week
Three things change at once in late November and December:
- Fewer working days. Thanksgiving falls on Thursday, November 26, 2026. Christmas Day is Friday, December 25, and New Year's Day is Friday, January 1, 2027. Many plants and receivers also close the day after, or the whole week between Christmas and New Year.
- Carrier networks run differently. Carriers publish holiday schedules. LTL terminals may close or run reduced service, and transit times quoted on a normal week may not hold. Freight that needs a cross-dock can stop for days.
- Capacity and rates move. Many shippers try to move freight in the same short windows, and drivers take time off. Spot quotes on busy lanes can rise and tender acceptance can drop. The size of the change varies by lane and year, so check your own quotes instead of trusting a rule of thumb.
What a good holiday plan looks like
A good plan is short and specific. It lists the closures, the cutoff date for each lane, the loads at risk and the person who decides each kind of exception. It is written down two to four weeks ahead and shared with sales, customer service and the warehouse, not only with logistics.
If your company closes for the holidays too, read what happens to open shipments during a holiday closure. That guide covers loads in transit while your own team is away. This article covers the wider problem: carriers and receivers closing on their own schedules.
Want to check your own December loads?
Let's review your December shipments and pickup dates. You don't need to prepare anything: Cartage maps the workflow with you on the call.
See it on your own loads. Wilson, by Cartage, is an AI logistics agent that quotes, books, tracks, audits and pays for freight with your approved carriers.
Book a demo →How do you build a holiday freight plan step by step?
Work from the closures backward to the ship dates, then confirm each load. The steps below take a few hours the first year and less after that, because most of the calendar repeats.
Step 1: Collect every closure in one place
Start with three lists:
- Your own sites. Plant and warehouse shutdown days, reduced shifts and the last day the dock loads outbound trucks.
- Your carriers. Each approved carrier's holiday schedule: closed days, reduced service days, and any change to pickup or delivery service. Ask for it in writing if it has not arrived.
- Your receivers. Each major customer's receiving hours over the holidays, including days the dock is closed and days it takes appointments only.
Put them on one calendar, by date. A spreadsheet works. What matters is that the three lists sit next to each other.
Step 2: Set a last ship date per lane
For each main lane, work backward from the receiver's last open day before the holiday. Subtract the carrier's transit time, then add a buffer for the slower holiday network. The result is the last date freight should leave your dock on that lane.
Consider a hypothetical LTL lane with a normal transit of three business days. The receiver's last open day before Christmas is Wednesday, December 23. Counting back three business days from December 23 gives Friday, December 18. With one extra day of buffer, the last ship date becomes Thursday, December 17. Any order on that lane that is not ready by then should ship after the holiday, and the customer should hear that now, not on December 22.
Step 3: Find the loads at risk
Compare open orders against the last ship dates. Mark three groups:
- Safe. Ready before the last ship date with room to spare.
- Tight. Ready close to the last ship date. These need early booking and close tracking.
- Late. Not ready until after the last ship date. These need a decision: expedite, ship after the holiday or split the order.
Step 4: Pull pickups forward where you can
If production allows, ship tight loads a day or two earlier. A load that sits in your warehouse is easier to manage than a load that sits in a closed terminal. Talk to the warehouse and production planners: often a pickup can move up a day if someone asks early.
Step 5: Book early and quote the busy lanes
Book holiday-week loads earlier than usual. On lanes where spot capacity gets tight, request quotes earlier and keep a second approved carrier ready. If quotes come in over the lane limit, the approval rule decides, not whoever happens to be at the desk.
Step 6: Confirm every date in writing
For each tight load, get written confirmation of the pickup date, the expected delivery date and the receiver's appointment or open hours. A general holiday notice does not confirm a specific load.
Step 7: Tell customers before they ask
Send customers the new ship and delivery dates as soon as they are clear. A customer told on December 10 that an order will arrive January 4 can plan. A customer told on December 23 cannot.
Which closures and capacity changes should you plan around?
Plan around four kinds of change: carrier terminal closures, reduced carrier service, receiver closures and capacity or rate shifts. Each one causes a different failure and needs a different check.
Carrier terminal closures
LTL freight moves through terminals. If the origin, a cross-dock or the destination terminal closes, the freight waits. The carrier's transit time does not count closed days, so a three-day transit can take a week across a holiday.
What to check: the carrier's holiday schedule for each terminal on the route, not just the company-wide notice. Ask the carrier directly when a lane matters.
Reduced service days
Some carriers run partial service around holidays: pickups but no deliveries, or deliveries only in certain areas. A load can be picked up on a reduced service day and still not move until the network is fully open.
What to check: whether the pickup day and every day in transit are full service days for that carrier.
Receiver closures
A truck that arrives at a closed dock is a failed delivery. It can mean a redelivery fee, storage charges or a driver who leaves and returns days later. Many receivers also change hours in the weeks around the holidays: shorter shifts, appointments only, or no receiving on Fridays.
What to check: each customer's receiving hours for every date in the window. If a customer has several sites, check each one.
Capacity and rate shifts
Holiday weeks compress demand into fewer days. Truckload spot quotes can rise on busy lanes, and tender rejections can climb as carriers choose among more offers. This guide does not give a percentage, because it changes by lane, by year and by mode. Your own recent quotes are a better guide than any average.
What to check: quotes on your main lanes two to three weeks before the holiday, compared with the same lanes a month earlier.
How the four changes show up on a load
| Change | What fails | Early sign | What to do |
|---|---|---|---|
| Terminal closure | Freight stops in transit for days | Carrier holiday notice; transit quote longer than usual | Ship earlier or after the holiday |
| Reduced service day | Pickup happens but freight does not move | Pickup confirmed, no movement scan | Avoid shipping on reduced days for urgent loads |
| Receiver closure | Delivery attempt fails at a closed dock | Receiver hours missing or not confirmed | Confirm hours in writing; set appointments early |
| Capacity tightness | Tender declined; spot quotes over the limit | Fewer quotes returned; slower acceptance | Book earlier; keep a second approved carrier ready |
| Rate increase | Load costs more than budget | Quotes above the lane target | Apply approval rules; decide which loads can wait |
When the carrier offers a later date
Around the holidays, carriers sometimes accept a load but say they cannot pick up until a later day. That later date may still work, or it may break the delivery. Treat it as a change that needs a decision. Update the expected date on the load, keep the agreed date on record and let the person who owns the customer decide whether to accept it, move to another approved carrier or ship after the holiday.
What should you decide before people go on leave?
Before people leave, decide who can approve each kind of exception, where alerts go and which loads can wait. Most holiday failures are not caused by bad carriers. They are caused by a decision nobody had the authority to make.
Rule 1: Name a decision owner for each exception
Write down who decides:
- A pickup date change.
- A rate above the lane limit.
- An expedite.
- Holding an order until after the holiday.
- Splitting an order to ship part of it before the closure.
Each one needs a primary person and a backup, with dates. "Ask the logistics manager" does not work on December 24 if the logistics manager is out.
Rule 2: Decide which loads can wait
Some freight can ship in January with no harm. Some cannot: a customer's production line, a promised delivery, product with a short shelf life. Sort open orders by what happens if they arrive late. Put effort on the loads where lateness costs the most.
Rule 3: Set a cutoff for new orders
Tell sales and customer service the last date an order can be entered and still ship before each closure. Orders after the cutoff ship after the holiday, unless the decision owner approves an exception. The guide on getting logistics ready for peak season covers how to agree on cutoffs with sales in more detail.
Rule 4: Keep tracking during the closure
Loads in transit do not stop because the office closes. Someone, or something, needs to watch them. That means checking the carrier's status, chasing a missing update and telling the right person when a load stalls.
Common mistakes
Trusting normal transit times. A transit quote from October does not hold in late December. Ask again.
Treating a carrier's holiday notice as confirmation. The notice says when the carrier is closed. It does not confirm your load's pickup or delivery.
Shipping on the last possible day. The last ship date has no margin for a missed pickup. Aim for the day before.
Forgetting the receiver. Many teams check the carrier calendar and forget the customer dock, which is the most common closed door.
Letting date changes slip by. A carrier that moves a pickup by a day can push a delivery past a closure. That change needs a person's decision, not silent acceptance.
No record of what was agreed. After the holidays, disputes come up over redelivery fees and storage. Without written confirmations, they are hard to settle. See appointment records that support a detention charge for the kind of records that hold up.
A short decision guide
| Situation | Decision |
|---|---|
| Order ready well before the last ship date | Book early and track normally |
| Order ready on the last ship date | Book now; confirm receiver hours; keep a second approved carrier ready |
| Order ready after the last ship date | Ship after the holiday unless the decision owner approves an expedite |
| Carrier offers a later pickup | Present the option to the decision owner; update the expected date; keep the agreed date |
| Spot quote above the lane limit | Follow the approval rule; check whether the load can wait |
| Receiver hours unknown | Do not ship until hours are confirmed in writing |
What does a holiday freight checklist look like?
Use one checklist per holiday period, owned by one person, and review it a week before and a week after. The items below cover the work most teams miss.
Four weeks before
| Item | Question to answer | Owner |
|---|---|---|
| Site closures | Which days do our plants and warehouses close or run short shifts? | Operations |
| Carrier schedules | Has each approved carrier sent its holiday schedule in writing? | Logistics |
| Receiver hours | Do we have holiday receiving hours for each main customer site? | Customer service |
| Last ship dates | What is the last ship date for each main lane? | Logistics |
| Order cutoffs | Has sales been told the last order date for each closure? | Sales and logistics |
| Decision owners | Who approves date changes, rates over limit, expedites and holds? | Logistics manager |
Two weeks before
| Item | Question to answer | Owner |
|---|---|---|
| Loads at risk | Which open orders are tight or late against the last ship dates? | Logistics |
| Early pickups | Can production ship any tight loads earlier? | Production and logistics |
| Quotes on busy lanes | Have we quoted the lanes where capacity is tight? | Logistics |
| Second carrier | Is a second approved carrier ready on each critical lane? | Logistics |
| Customer notices | Have customers with late orders been told the new dates? | Customer service |
The week of the holiday
- Confirm each tight load's pickup and delivery in writing.
- Confirm appointments at receivers that require them.
- Track every load in transit at least once a day.
- Log every date change and who approved it.
- Hand off open issues to the named decision owner before leaving.
The week after
- Check that every load picked up before the holiday was delivered.
- Request missing PODs.
- Review carrier invoices for redelivery, storage or holiday surcharges, and check each one against what was agreed.
- Note what went wrong and update next year's calendar.
Keep the calendar for next year
Most of the holiday calendar repeats. Save the carrier schedules, receiver hours and last ship dates with notes on what worked. Next November, the plan starts from last year's version instead of a blank page.
How does Wilson, by Cartage, handle freight around the holidays?
Wilson, by Cartage, is an AI logistics agent that quotes, books, tracks and pays freight for manufacturers and distributors, and it follows the company's rules when holiday closures change what a load can do. Traditional logistics software gives teams information. Wilson executes the work required to move shipments forward. Think of it as a free logistics department: what big shippers build over years, Wilson does from day one, in four parts.
The labor. Wilson does the work from the first quote to the final POD: quotes, bookings, paperwork, tracking and carrier follow-ups, by email, phone calls, texts, Slack and Microsoft Teams. It checks carrier availability before booking. If a carrier says it cannot pick up until a later day, Wilson does not accept that silently: it presents the option to the team, updates the expected date on the shipment and leaves the agreed date unchanged. The team decides on any date change. When a deadline to quote, pick up or deliver passes and the order is still incomplete, Wilson flags it to the team. During the holidays, it keeps tracking loads in transit with the best source available for each load: a carrier API or EDI, GPS or ELD data where the carrier shares it, the carrier's website by PRO number, and email or phone calls when nothing else is current. It follows up with carriers by phone and email until it gets an answer.
When a load fails, such as a missed pickup or a cancellation, Wilson contacts the carrier, tells the team, tells the customer if configured and starts rebooking from the approved carrier list automatically within the rules or after approval.
The data. Wilson keeps every order, load, quote, rate, document and contact on record as it works, connected to the company's ERP. Wilson replaces the TMS for freight execution and connects to the company's ERP. It keeps rules and preferences the team can edit, such as a customer site that only receives in the morning. When the team changes something on one load, Wilson treats it as a change to that load. If it looks like it should become a rule, Wilson asks the team first. Every message, confirmation and change is kept in the shipment's change history, so after the holidays the team can see who agreed to each date.
Wilson works with SAP, NetSuite, Microsoft Dynamics 365, Oracle, Infor, Epicor, Sage, Acumatica and other ERP environments, with the exact connection depending on the customer's data flow and scope.
The network. Wilson gets better freight rates on every lane because the shipper's volume counts with every other Wilson customer's. The network includes carriers and brokers. The company still approves who hauls its freight, and Wilson books only approved carriers. Wilson negotiates toward the company's rate targets within approval limits, and rates outside the limits go to the logistics team, which matters when holiday quotes rise.
The payments. Wilson audits every carrier invoice against the rate confirmation and the POD before money moves, then pays carriers from the Wilson Wallet. A redelivery or storage charge that was not agreed, or an invoice over the rate, waits for a person.
Control stays with the company. Wilson starts with assisted execution, the company sets approval limits, and routine actions can run automatically within those rules as the workflow is proven. Teams can start with a subset of shipments, such as a few lanes, before expanding.
Pricing
Wilson is free on Wilson's network: the shipper pays the freight rate and nothing on top. When a shipper keeps its own carriers, the fee is 2% to 0.5% of what Wilson pays them, falling with volume. There are no seat fees, no setup cost and no contract. Timing depends on scope: most teams start on a few lanes and expand from there.
FAQs
Can Wilson help us plan freight around the holidays?
Yes. Wilson, by Cartage, an AI logistics agent, quotes and books loads with the company's approved carriers, checks carrier availability before booking and tracks loads in transit. If a carrier offers a later pickup date, Wilson presents it to the team and leaves the agreed date unchanged until the team decides.
When should we start planning holiday freight?
Four weeks before the first closure is a good start. That leaves time to collect carrier schedules and receiver hours, set last ship dates and tell sales the order cutoffs. Two weeks out, focus on the loads at risk.
Do carriers close on Thanksgiving and Christmas?
Many carriers close or run reduced service on major holidays, and LTL terminals often follow their own schedule. The details differ by carrier and by year. Ask each approved carrier for its holiday schedule in writing.
How much do freight rates go up around the holidays?
It depends on the lane, the mode and the year. Truckload spot quotes on busy lanes can rise and capacity can tighten, but no single percentage holds everywhere. Quote your main lanes two to three weeks ahead and compare with recent quotes.
What is a last ship date?
It is the last day freight can leave your dock and still reach the receiver before it closes. Work it out per lane from the receiver's last open day, the carrier's transit time and a buffer for the slower holiday network.
What happens if a load arrives at a closed receiver?
The delivery usually fails. The carrier may charge a redelivery fee or storage, and the freight waits until the dock reopens. Confirming receiver hours in writing before shipping prevents most of these cases.
Should we ship early or late around a holiday?
Ship early when the load is ready and the receiver can take it. Freight that waits in your own warehouse is easier to manage than freight stuck in a closed terminal. If a load cannot reach the receiver before the closure, ship it after.
Who should decide on exceptions while people are out?
Name a primary person and a backup for each type of exception: date changes, rates over the limit, expedites and holds. Write the names and dates down and share them with the team and with anyone who sends alerts.
How does Wilson handle a holiday surcharge on an invoice?
Wilson audits each carrier invoice against the rate confirmation and the POD. A charge that was not on the rate confirmation, or an invoice over the agreed rate, is held for a person before payment.
Does Wilson keep working when our office is closed?
Wilson keeps tracking and following up on loads under the company's rules while the team is away. Decisions outside those rules, such as a date change or a rate above the limit, wait for the person the company has named.