We're moving our warehouse. How do we keep freight running during the move?
How do you keep freight running during a warehouse move?
Consider a hypothetical industrial distributor moving out of a 120,000-square-foot building into a new one 40 miles away. The lease on the old building ends on the last day of the month. The plan gives the move three weeks: one week to stage the slow-moving stock, one week to move the bulk of the inventory, and one cutover week when the old building stops shipping and the new one starts. The facilities plan is detailed: racking, forklifts, the IT closet, the phone lines. The freight plan is one line: "notify carriers."
On the Tuesday of the cutover week, an LTL carrier sends a driver to the old building for a customer order that now sits on a pallet at the new one. A supplier truck arrives at the old dock with 22 pallets of inbound stock and finds the doors locked. A customer's receiving team calls to ask why its order shipped from an address it doesn't recognize. None of these problems is about moving inventory. All of them are about freight data that didn't move with the inventory.
To keep freight running during a warehouse move, treat the move as three freight flows (outbound customer orders, inbound supplier deliveries and transfer loads between the buildings), set a dated rule for which site ships each order, update every address and dock rule in every system that books freight, and tell carriers, customers and suppliers in writing before the cutover week. The trucks will show up. The job is to make sure they show up at the right building, at a time the dock can take them, with paperwork that matches where the freight really is.
The three freight flows in a move
Every move has the same three flows, and each one has a different owner and a different failure.
- Outbound customer orders keep shipping throughout the move. The risk is a pickup sent to the wrong building, or an order promised from stock that is on a trailer between the two sites.
- Inbound supplier deliveries keep arriving. The risk is a supplier, or the supplier's carrier, delivering to the old address after it closes, or arriving at the new building before its receiving dock is ready.
- Transfer loads move the inventory itself. The risk is a load that leaves without a count, or a load that arrives when the new dock is full of outbound freight.
A move plan that only covers the transfer loads leaves the other two flows to chance, and they are the two flows customers and suppliers notice.
Why freight data is the weak point
Carriers book pickups against the ship-from address on the shipper's account. Suppliers ship to the ship-to address on the purchase order. Customers see the ship-from address on the bill of lading. Parcel carriers often run scheduled daily pickups tied to one address. Each of those addresses lives in a different place: the ERP, the carrier's own system, the supplier's order system, a label template, a saved spreadsheet. A move changes one fact, the address, in all of those places at once. Any place that doesn't get updated sends a truck to an empty building.
Who should own freight during the move
Name one person who owns freight for the whole move. They don't book every load, but they own the order-routing rule, the notice list and the cutover-week load list. Without that owner, freight falls between the warehouse team and customer service.
Let's review your move plan and the loads that fall in the cutover week. You don't need to prepare anything: Cartage maps the workflow with you on the call.
See it on your own loads. Wilson, by Cartage, is an AI logistics agent that quotes, books, tracks, audits and pays for freight with your approved carriers.
Book a demo →How should you plan freight for the move, week by week?
Work backward from the cutover date and give every freight change a date and an owner. Most freight problems in a move come from changes made too late, or made in one system and not the others.
Eight weeks before
Write the freight inventory of the move. List every carrier that picks up at the old building, every supplier that delivers there, every customer that receives from it, every scheduled or recurring pickup, and every system that holds the old address. Include the ones people forget: the parcel pickup that runs every afternoon, the drayage carrier that returns empty containers, the courier for samples, the supplier that ships once a quarter.
Confirm the new building's details in writing: the street address as carriers will need it, the dock door count, receiving and shipping hours, whether appointments are required, whether trucks can stage overnight, the gate or check-in process, the contact name and phone number for the dock, and any limits such as trailer length or a weight limit on the access road.
Six weeks before
Decide the order-routing rule: which site ships which orders from which date. Decide how transfer loads will move (dedicated trucks, a contracted shuttle, spot truckloads or LTL for small lots) and book the capacity. If the move is large, ask carriers early for a shuttle rate, because a few weeks of steady round trips is a different job from one-off loads.
Four weeks before
Send written notices to carriers, suppliers and customers with the effective date and the new details. Ask each one to confirm. Set up the new address in the ERP as a new ship-from and ship-to location, but don't switch the default yet. Prepare the new bill of lading template, pallet labels and packing slips with the new ship-from address, ready to use on the effective date.
Two weeks before
Chase every notice that hasn't been confirmed. Check open purchase orders with delivery dates after the cutover and make sure each one shows the new ship-to address. Check open customer orders with ship dates in the cutover week and assign each one to a site under the routing rule. Confirm the transfer load schedule with the warehouse teams at both ends.
Cutover week
Run from one load list. Every load that touches either building during the week is on it: outbound, inbound and transfer, with its site, appointment, carrier and owner. Check the list twice a day. Move the scheduled parcel pickup on the day the old building stops shipping, not before and not after.
How do you run transfer loads between the old and new building?
Treat each transfer load like a customer shipment: a booked carrier, a bill of lading, a count at both ends and a delivery confirmation. Transfer loads are where inventory gets lost during a move, because they feel internal and get handled informally.
Choosing how to move the inventory
| Option | When it fits | What to watch |
|---|---|---|
| Dedicated truck and driver for the move | Many round trips a day over a short distance | Daily cost even on slow days; dock time at both ends |
| Shuttle rate from a truckload carrier | Steady volume over several weeks | Agree the number of trips per day and the cancellation terms |
| Spot truckload per load | Uneven volume, or long distance between sites | Price changes from day to day; capacity in busy weeks |
| Drop trailers | One dock loads faster than the other unloads | Trailer count, yard space and trailer rental charges |
| LTL for small lots | Last odds and ends, or a few pallets of fast movers | Terminal handling, transit time and class rules |
| Own fleet | The company already runs trucks between sites | Driver hours and the outbound loads those trucks normally run |
Most moves use more than one option: a shuttle or drop trailers for the bulk of the stock, and LTL or a few spot loads for the tail.
Paperwork for a transfer load
Every transfer load should carry a bill of lading, even when the shipper and consignee are the same company. The BOL shows the carrier what it is moving and gives the company a document to claim against if something is damaged. List the pallet count, piece count and weight. Seal the trailer when the load is full and record the seal number on the BOL. At the new building, the receiving team checks the seal, counts the pallets and signs the BOL with any exceptions noted.
Counting at both ends
The ERP should know where every pallet is at every moment. A common approach is to move inventory into an "in transit" location when the transfer load leaves the old building, and into the new building's locations when it is received. A pallet that leaves and never gets received shows up as in-transit stock that ages, which makes it easy to find. A pallet that moves without any transaction disappears from both buildings.
Protecting the dock at the new building
The new building's dock has to receive transfer loads, receive supplier deliveries and, from the effective date, ship customer orders. If the transfer loads take every door from 7 am to 3 pm, outbound pickups will wait. Set aside doors or time windows for outbound and inbound freight, and schedule transfer loads around them. Drivers waiting at a crowded dock add detention charges. The American Transportation Research Institute found that trucks were detained at 39.3% of stops in 2023, with more than 135 million hours of detention, so a dock that is short of doors during a move is exactly the kind of place where detention starts.
Which site ships each open order, and which mistakes send trucks to the wrong building?
Write one routing rule for open orders, based on the ship date and on where the stock is, and send dated notices to everyone who books freight against either address. Without a written rule, each customer service rep decides on their own, and pickups go to the wrong building.
A routing rule for open orders
A simple rule covers most moves:
- Orders with a ship date before the cutover date ship from the old building.
- Orders with a ship date on or after the cutover date ship from the new building.
- If the stock for an order has already moved, the order ships from wherever the stock is, and the ship-from address on the order changes to match.
- Orders that need stock from both buildings either wait until the stock is together, or ship in two parts with the customer's agreement.
When an order, its stock and its booking disagree, the stock wins: the order ships from where the freight physically is, and the ship-from, the booking, the BOL and the customer's notice change to match. When a carrier also changes the pickup time, make sure the right building's dock hears about it; see what happens when a carrier reschedules a pickup and the warehouse misses it.
Split orders and partial shipments
Some orders will be split by the move: half the lines are still on the old racks, half are on a trailer. Decide in advance whether the company ships partials during the move. Some customers accept two deliveries; others charge for it or refuse it.
Mistakes that send trucks to the wrong building
- The order moved, the booking didn't. Check every booking made in the cutover window against the routing rule, and confirm each cutover-week pickup with the carrier by address, not only by date.
- Recurring parcel pickups keep running at the old address. Give every scheduled pickup its own start and stop date on the move plan.
- Old dock rules on new bookings. From the effective date, write the new building's hours and appointment rule into every booking and delete the old ones.
- Paperwork still shows the old ship-from. Switch BOL and label templates on the effective date and check the first ones printed at the new building.
- Rates from the old origin. Even a short move can change the origin terminal or zone, so confirm rates from the new origin before booking.
Who needs to be told what
| Who | What they need | How to confirm |
|---|---|---|
| Carriers that pick up | New ship-from address, effective date, dock hours, appointment rule, dock contact, any account or pickup changes | Written acknowledgment from each carrier; a test booking for the first pickup |
| Parcel carriers | New address for the scheduled daily pickup, start and stop dates | Confirmation of the new pickup schedule |
| Suppliers | New ship-to address on every open purchase order, receiving hours, appointment rule | Revised PO acknowledgment; first delivery appointment booked |
| Inbound carriers booked by suppliers | The supplier usually tells them, so ask the supplier to confirm it did | Delivery appointment request at the new building |
| Customers | New ship-from address, the date, and any change to delivery timing during the move | Acknowledgment from the receiving contact, not only the buyer |
| Customs brokers, for cross-border freight | New address for import and export documents | Updated paperwork on the first shipment |
| Internal teams | Customer service, sales, accounts payable and the warehouse at both sites | A shared copy of the routing rule and the cutover load list |
Updating the freight systems
The address change has to reach every place that books, documents or bills freight: the ERP's warehouse and location records, the default ship-from on customer orders, the ship-to on purchase orders, the BOL and label templates, any carrier portals where the company books pickups, any saved quotes and rate agreements tied to the old origin, and the company's own spreadsheets and email templates.
For companies that will run both buildings for a while, or will keep more than one site after the move, the rules in managing freight across multiple warehouses apply from the day the new building opens.
What should a freight cutover checklist include?
Use one checklist for the cutover, owned by the freight owner and reviewed with the warehouse teams at both buildings. The checklist below covers the freight side of a typical move.
| Item | When | Owner | Done when |
|---|---|---|---|
| Freight inventory: carriers, suppliers, customers, recurring pickups, systems with the old address | 8 weeks before | Freight owner | List reviewed with warehouse and customer service |
| New building details: address, doors, hours, appointment rule, check-in, contact, limits | 8 weeks before | Facilities and freight owner | Written down and shared |
| Order-routing rule for open orders | 6 weeks before | Freight owner and customer service | Approved and shared |
| Transfer load plan and capacity booked | 6 weeks before | Freight owner | Carrier confirmations on file |
| Rates from the new origin confirmed | 4 weeks before | Freight owner | Rate confirmations or carrier emails on file |
| Notices sent to carriers, suppliers and customers | 4 weeks before | Freight owner | Every recipient listed with a send date |
| New ship-from and ship-to set up in the ERP | 4 weeks before | ERP owner | Test order created and cancelled |
| New BOL, label and packing slip templates ready | 2 weeks before | Freight owner | Test documents printed |
| Every notice acknowledged | 2 weeks before | Freight owner | No open acknowledgments |
| Open POs updated with the new ship-to | 2 weeks before | Purchasing | Revised PO acknowledgments received |
| Open customer orders assigned to a site | 1 week before | Customer service | Every order in the window has a site |
| Recurring and parcel pickups moved | Cutover day | Freight owner | New pickup schedule confirmed |
| Cutover load list reviewed twice a day | Cutover week | Freight owner | Every load has a site, appointment and owner |
| First invoices from the new building checked | 2 to 4 weeks after | Freight owner or accounts payable | Charges match the rate confirmations |
| Old-address arrivals logged and fixed at the source | Until the lease ends | Freight owner | No arrivals at the old building in the last two weeks |
How does Wilson, by Cartage, keep freight moving during a warehouse move?
Wilson, by Cartage, is an AI logistics agent that quotes, books, tracks, documents, audits and pays freight for manufacturers and distributors, so the transfer loads, customer pickups and supplier deliveries of a move run from one record while both buildings are live. Traditional logistics software gives teams information. Wilson executes the work required to move shipments forward.
Wilson works as the company's free logistics department: what big shippers build over years, Wilson does from day one. For a move, each of the four parts of that department has a specific job.
The labor during the move
The labor is the booking and follow-up work that multiplies in a move. Wilson requests quotes for transfer loads and customer orders from the company's approved carriers, compares them on total cost and negotiates toward the company's rate targets within approval limits. It books the chosen carrier with written acceptance and a rate confirmation, schedules pickups at the right building, and generates the bill of lading, packing slips and pallet labels with the ship-from address of the site that is shipping. It tracks each load with the best source available for that carrier, and when a pickup is missed or a carrier cancels, it contacts the carrier, tells the team and starts rebooking from the approved carrier list within the rules or after approval. Carriers hear from Wilson by phone, email and text, and by API or EDI where the carrier supports it. Wilson checks carrier availability before booking; if a carrier can only pick up on a later day, Wilson presents that option to the team and leaves the agreed date unchanged until the team decides. The team doesn't chase carriers through the cutover week.
The data for both buildings
The data is where the move's new facts live. Wilson keeps every order, load, quote, rate, document and contact on record as it works, connected to the company's ERP. It also keeps memories and rules, learned from its own work or added by the team, such as "the new building takes appointments only, from 7 am to 1 pm" or "transfer loads use doors 5 to 8 before noon". The team can edit them, which matters in a move, because the rules change on a set date. Wilson replaces the TMS for freight execution and connects to the company's ERP. Wilson works with SAP, NetSuite, Microsoft Dynamics 365, Oracle, Infor, Epicor, Sage, Acumatica and other ERP environments, with the exact connection depending on the customer's data flow and scope. Whether changes such as a new ship-from address are written back to the ERP depends on that scope; confirm it in discovery. Every message, confirmation and change is kept in the shipment's change history, and records are searchable and exportable.
The network for extra capacity
The network helps when a move needs more trucks than usual. The shipper's volume counts with every other Wilson customer's, which can bring better freight rates on its lanes, and the network includes carriers and brokers. The company still approves who hauls its freight: Cartage can suggest additional carrier capacity, but the company approves each carrier before Wilson uses it.
The payments after the move
The payments catch the charges a move tends to create. Wilson requests and files each POD, audits every carrier invoice against the rate confirmation and the POD before money moves, and pays carriers from the Wilson Wallet. When an invoice is over the rate, for example a detention charge at the new dock or a rate from the old origin, Wilson flags it and asks the carrier why before paying. Invoices over the rate or outside the rules wait for a person.
What Wilson does in the cutover week
| Situation | What Wilson does | When a person steps in |
|---|---|---|
| A transfer load needs a truck | Requests quotes from approved carriers, books within limits, issues the BOL | When the rate is outside the approval limits |
| An order's stock moved early | Books the pickup at the building where the order ships, per the order record | When the routing rule doesn't say which site ships it |
| New dock hours take effect | Applies the rule the team set to every new booking | When the team changes the rule |
| A carrier misses a pickup | Contacts the carrier, tells the team, rebooks from the approved list within the rules | When no approved carrier can make the date |
| A customer needs to know about a delay | Tells the customer by email or SMS, if configured | When the customer relationship needs a call from the team |
| An invoice arrives above the rate | Flags it and asks the carrier why before paying | When the charge is outside the rules |
Wilson starts with assisted execution. The company sets approval limits, and routine actions can run automatically within those rules as the workflow is proven. People reach Wilson by email, Microsoft Teams, Slack, WhatsApp, text or phone. Wilson handles LTL, FTL, ocean, drayage, parcel and cross-border freight. It is not a freight broker or a customs broker, and it doesn't plan the warehouse network or the physical move itself.
Pricing
Wilson is free on Wilson's network: the shipper pays the freight rate and nothing on top. When a shipper keeps its own carriers, the fee is 2% to 0.5% of what Wilson pays them, falling with volume. There are no seat fees, no setup cost and no contract. Timing depends on scope: most teams start on a few lanes and expand from there.
FAQs
Can Wilson keep freight moving while we move warehouses?
Yes. Wilson, by Cartage, an AI logistics agent, books and tracks transfer loads and customer shipments from the company's approved carriers, applies the dock hours and appointment rules the team sets for each building, and keeps every load on one record during the move. Rates outside the approval limits and situations the rules don't cover go to the team.
How far ahead should we plan freight for a warehouse move?
Start about eight weeks before the cutover with an inventory of every carrier, supplier, customer, recurring pickup and system that holds the old address. Notices should go out about four weeks before, which leaves time to chase confirmations.
Should transfer loads between our own buildings have a bill of lading?
Yes. A BOL tells the carrier what it is moving, records the pallet count and seal number, and gives the company a document to rely on if freight is damaged or short. The receiving team signs it with any exceptions noted.
Which site should ship an order during the cutover week?
Use a dated rule: orders before the cutover date ship from the old building, orders after it from the new one, and any order whose stock already moved ships from wherever the stock is. When an order changes site, the booking, the BOL and the customer's notice change with it.
How do we stop carriers from sending trucks to the old address?
Send written notices with an effective date, get each carrier to acknowledge them, confirm every cutover-week pickup by address, and ask carriers to deactivate the old address on the company's account after the move. Log any truck that still arrives at the old building and fix the source of the booking.
Do freight rates change when a warehouse moves?
They can. A new origin can mean a different terminal, zone or lane rate, even for a short move. Ask carriers to confirm rates from the new origin before booking, and check the first invoices from the new building against the rate confirmations.
What should we tell customers about a warehouse move?
Tell them the new ship-from address, the effective date and any change to delivery timing during the move. Send the notice to the receiving contact as well as the buyer, because the receiving team is the one that will see the new address on the BOL.
How do we keep inbound supplier freight from going to the old warehouse?
Update the ship-to on every open purchase order, ask each supplier with deliveries in the move window to confirm the new address in writing, and keep a phone number at the old building until the lease ends. Suppliers often book their own carriers, so confirm that the supplier told its carrier too.
Sources
- American Transportation Research Institute, "New Research Documents Substantial Financial and Safety Impacts from Truck Driver Detention," September 2024: https://truckingresearch.org/2024/09/new-research-documents-substantial-financial-and-safety-impacts-from-truck-driver-detention/